1 |
Minutes of Meeting, 17/10/2000 @ 7pm. |
2 |
Location: 2 Mead Way |
3 |
|
4 |
Present: ab11, pjm2, tdb1 |
5 |
Absent: ajm4 |
6 |
|
7 |
Initial discussions surrounded the fact that iau wants a |
8 |
plan from us pretty soon. However, we soon digressed to the |
9 |
other things we needed to get working on. These are as |
10 |
follows; |
11 |
|
12 |
- Produce a feature list - re: first minutes |
13 |
- Produce an "implementation phases" document, based on the |
14 |
feature list |
15 |
- Prepare the above two for review by jc (and iau?) |
16 |
|
17 |
- Set ourselves some rough milestones (ie. phase 3 by xmas |
18 |
etc...) |
19 |
- With the above in mind produce a plan for the overall |
20 |
project and assign initial roles. |
21 |
|
22 |
- Define the Interfaces of the various server classes |
23 |
- Define the Protocols for cross-network data |
24 |
|
25 |
Discussions about all of our limited knowledge of C/C++ put |
26 |
an end to the plan that one of us could actually write all |
27 |
the host programs :) |
28 |
|
29 |
Some questions and points were raised |
30 |
|
31 |
- Differences between Solaris SPARC/Intel - will program run |
32 |
on both ? |
33 |
- The "Client Interface" in the server - how much "thinking" |
34 |
will it do, and how much will be left to the client. |
35 |
(Thinking about bottlenecks). |
36 |
- Database, need to get a machine sorted, and pick database. |
37 |
- Would multicasting work for server to client |
38 |
communications ? |
39 |
|
40 |
Next the document on the Implementation Phases was drawn up. |
41 |
It's only provisional at this stage, but gives us some |
42 |
initial ideas. It was noted that by using "phases" we can |
43 |
have milestones/breaks for testing, documentation |
44 |
and review. This would ensure that we keep things under |
45 |
control, and don't get swamped in code. It was also |
46 |
mentioned that using phases would help to keep the whole |
47 |
project in sync - ie. the server code would not run off |
48 |
ahead of the host code. |
49 |
|
50 |
pjm2 leaves at 7:45pm, whilst ab11 & tdb1 continue with |
51 |
implementation phases document. |
52 |
|
53 |
The final Implementation Phases document is seperately |
54 |
stored. |
55 |
|
56 |
Meeting is concluded at 8:30pm to watch MIB. |