ViewVC Help
View File | Revision Log | Show Annotations | Revision Graph | Root Listing
root/i-scream/projects/cms/documentation/minutes/minutes-20001023.txt
Revision: 1.1
Committed: Wed Oct 25 18:06:09 2000 UTC (24 years, 1 month ago) by tdb
Content type: text/plain
Branch: MAIN
CVS Tags: PROJECT_COMPLETION, HEAD
Log Message:
Minutes from meeting on 23/10/2000.

File Contents

# User Rev Content
1 tdb 1.1 Minutes of Meeting, 23/10/2000 @ 10:30 / 2.00
2     Location: UKC Computer Science Meeting Room
3    
4     Present: ab11, ajm4, pjm2, tdb1
5     Absent: none
6    
7     Initial discussion was on the first deliverable for the
8     project. This consists of an initial plan of the project,
9     including rough outlines of the types of deliverables
10     required and estimated time due to be spent on each section
11     of the project.
12    
13     It was estimated that a total of 1000 hours would be spend
14     on the project.
15    
16     Tim managed to untie the computer security cables without
17     breaking the plastic cable-ties. It was decided that this
18     was a *real* achievement and thus should be noted in these
19     minutes.
20    
21     Meeting is concluded @ 12:00
22    
23     Meeting was re-convened @ 2.00pm. The plan was finished off
24     with more detailed hours being placed on each section. It
25     was printed and delivered to iau, giving him time to review
26     it prior to the meeting on Wednesday.
27    
28     Meeting was concluded at 3.15pm.