Initial discussion was on the first deliverable for the |
8 |
project. This consists of an initial plan of the project, |
9 |
including rough outlines of the types of deliverables |
10 |
required and estimated time due to be spent on each section |
11 |
of the project. |
12 |
|
13 |
It was estimated that a total of 1000 hours would be spend |
14 |
on the project. |
15 |
|
16 |
Tim managed to untie the computer security cables without |
17 |
breaking the plastic cable-ties. It was decided that this |
18 |
was a *real* achievement and thus should be noted in these |
19 |
minutes. |
20 |
|
21 |
Meeting is concluded @ 12:00 |
22 |
|
23 |
Meeting was re-convened @ 2.00pm. The plan was finished off |
24 |
with more detailed hours being placed on each section. It |
25 |
was printed and delivered to iau, giving him time to review |
26 |
it prior to the meeting on Wednesday. |