1 tdb 1.1 Minutes of meeting 27/11/00 @ 2pm
2     Location: UKC Computer Science Meeting Room
3    
4     Present: ab11, ajm4, pjm2, tdb1
5     Absent: None
6    
7     AJ reported back that the configuration system is finished,
8     and has been fully documented in a seperate document. Paul
9     informed the group about the database bits he did, and the
10     changes to the filter setup. Ash said the Java host should
11     be checked into CVS later on. Tim told the group that the
12     TCP parts of the Filter were complete, and the whole system
13     was in a working as it stood.
14    
15     An issue was raised about the use of /experimental and
16     /source in the CVS repository. There was some confusion
17     between the group members over what should be put in each
18     section.
19    
20     It was agreed that code which would be part of the product
21     would be put into /source, whilst /experimental would be
22     used for seperate bits of code - generally those testing an
23     idea before it gets merged into the overall system.
24    
25     Next the group reviewed the current state of the code.
26     Everyone seemed happy with how things stood, and everyone
27     got a good understanding of how the whole system went
28     together.
29    
30     It was decided that Tim should try and put together some
31     coding standards based on ones used previously. These should
32     be adapted to suit the current situation, and then be
33     presented to the group. Once agreed, all code will be
34     checked to ensure adherance to the standards.
35    
36     The database was another issue raised. It would soon be
37     necessary to ensure all data is logged into the database,
38     and this requires some database design and planning. Paul
39     agreed to put together a design for the database for review
40     by the group. He also plans to look into, and implement, the
41     java side of the database connectivity, and the PHP user
42     interface.
43    
44     Before the next meeting Ash will have checked in the Java
45     host, and it should at least be able to send data to the
46     server. Paul will have a database design, and maybe some
47     documentation for the XML data. AJ will generate some more
48     documentation, and a nicer version of the GUI-based logger.
49     Tim will patch up a few of the missing bits around the
50     server, and produce some coding standards and logging
51     documentation.
52    
53     The next meeting will be on Wednesday afternoon after the
54     meeting with Ian. Meeting room is booked 3pm to 5pm.