| 1 |
Minutes of meeting 05/02/2001 @ 2pm |
| 2 |
Location: UKC Computer Science Meeting Room |
| 3 |
|
| 4 |
Present: ajm4, pjm2, tdb1 |
| 5 |
Absent: ab11 |
| 6 |
|
| 7 |
Ash was absent from this meeting after oversleeping and not |
| 8 |
making it to campus on time. The group waited for around an |
| 9 |
hour before commencing the meeting anyway. |
| 10 |
|
| 11 |
Initial discussions were, as usual, about the progress of |
| 12 |
the systems. A lot of work had been done since the last |
| 13 |
meeting, some due to the design change in the database. Paul |
| 14 |
put extensive work into completely rewriting the DBReporting |
| 15 |
tools, and they now run considerably quicker. AJ made the |
| 16 |
frontend of the client display nearly all the data in a |
| 17 |
graphical form, and changed more stuff "under the hood". Tim |
| 18 |
implemented the local client structure, on both the server, |
| 19 |
and a dummy client. |
| 20 |
|
| 21 |
After feedback in the week from jc with regard to our |
| 22 |
database size, the group decided it was worth discussing his |
| 23 |
opinions. The group could understand the viewpoint, but |
| 24 |
stuck by the long standing decision to use XML formatting |
| 25 |
for the data. However, it was decided to look into |
| 26 |
compression techniques, and possibly removing some of the |
| 27 |
unneeded tags (using attributes?). |
| 28 |
|
| 29 |
The group noted that time was slowly running out, and |
| 30 |
expressed concern on the development of the host. Ash was |
| 31 |
absent and unable to comment. There were 3 weeks remaining |
| 32 |
until project week, and a lot to do. |
| 33 |
|
| 34 |
On the whole, the group were happy with the milestones at |
| 35 |
present, with some parts being further behind than planned, |
| 36 |
but others further ahead. |
| 37 |
|
| 38 |
There will be no meeting with Ian this week. The next group |
| 39 |
meeting will be on Monday. |