1 tdb 1.1 Minutes of meeting 05/03/2001 @ 2pm
2     Location: UKC Computer Science Meeting Room
3    
4     Present: ab11, ajm4, pjm2, tdb1
5    
6     This meeting started with the long awaited demonstration to
7 pjm2 1.2 John... except he brought a few colleagues along :) With our
8     captive audience, we demonstrated the past 20 odd week's
9     work, and fortunately got lots of positive feedback. This
10 tdb 1.1 certainly boosted the confidence of the group as it made all
11 pjm2 1.2 the effort seem worthwhile. One comment worth nothing was: -
12 tdb 1.1
13 pjm2 1.2 "I wasn't expecting it to be quite so useful!"
14 tdb 1.1
15 pjm2 1.2 After the demonstration, the group proceeded to discuss
16     where to head next. Particular issues on the agenda were the
17 tdb 1.1 webpage front end, and the alerting mechanisms.
18    
19     Both AJ and Tim had spent a couple of very late nights
20     writing the alerting mechanisms (the local clients) for the
21     server. They noted that the logic behind it all was a lot
22     more complex than had been anticipated, and that it really
23     was a major part of the system. This work had been mostly
24     done for some basic data (CPU levels) and just needed to be
25     expanded to cover the rest. This was to be done over the
26     following week.
27    
28     Ash was pleased to report that the host was now working,
29     although there still existed a problem with packet size. All
30     the other issues with it crashing etc had been tidied up. He
31     again noted that he was keen to get some work done on the
32     webpage frontend.
33    
34     Paul said he had completed most tasks, including the winhost
35     and the DBReports. He volunteered to do some work on the
36     webpage frontend.
37    
38     The webpage frontend was something that needed doing. The
39     group agreeded it should be broken down into sections on
40     latest host data, latest alerts, and historical information
41     (db reports). These would all be tied together into one
42     easily navigatable interface, with a nice summary page. This
43     would tie closely with the alerting mechanisms discussed
44     above, so no plans for the actual implementation details
45     could be made at this stage.
46    
47     Another issue that evolved from this was the host sampling
48     data and sending averages, and alerts. Ash said logic was in
49     place to start this, and he had it planned. AJ pointed out
50     that the initial design for the host was to be as
51     lightweight as possible, and this would just complicate it,
52     especially when the same work is carried out in the server.
53     The topic wasn't completely resolved, although the group
54     seemed to agree that it shouldn't be a priority with the
55     short time left.
56    
57     The final issue was documentation. This would be looked at
58     over the week, and maybe another meeting arranged later on
59     to plan it.
60    
61     There will be a meeting with Ian at 2.15pm on Wednesday, and
62     the usual meeting on Monday at 2.15pm. There may be an extra
63     meeting in the week to discuss documentation.